The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków
The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.
The challenge
The Schumacher Packaging plant (now part of the Saica group) in Myszków needed to significantly increase energy efficiency and reduce dependence on rising electricity and heat costs, which are key in production processes such as paper drying. Initial plans assumed the installation of a 1 MW cogeneration unit, but detailed analysis revealed that the facility's actual energy needs were several times higher. The biggest challenge was adapting the infrastructure to supply a 4.4 MW engine – the existing LNG regasification station could not provide sufficient gas, and it was also necessary to integrate the new installation with the facility's extensive network of heat and energy sources.
Key challenge of the Myszków plant modernization:
- Scaling the gas installation – the initial 1 MW project was expanded to 4.4 MW, requiring the LNG regasification station to be increased by more than 100%.
- Integration of new and existing systems – connecting cogeneration with the gas boiler, coal CHP, and other installations required advanced design and network solutions.
- Flexibility in energy management – the plant needed the ability to smoothly switch and combine energy sources (steam, electricity, heat) depending on production needs.
Our approach
We approached the project comprehensively – from analyzing the facility's energy demand, optimizing the scale of the investment, to designing and executing the installation. The initial assumptions (1 MW) were reviewed and increased to 4.4 MW so that the installation would realistically meet the factory's needs. A key element was designing and expanding the LNG regasification station, enabling safe and stable supply to the cogeneration unit.
At the same time, we analyzed and planned the integration of the new cogeneration with existing energy sources – the coal CHP and gas boiler – creating a flexible system that allows energy production to be managed according to the plant's current demand.
Solution
As part of the investment, we designed and commissioned a modern 4.4 MW cogeneration unit operating on LNG. The installation produces both electricity and heat – 2.7 MW in hot water and 1,760 kg of steam per hour – efficiently covering the demand of technological processes.
As of September 2024, this is the largest LNG-powered cogeneration unit operating in southern Poland.
Scaling the gas installation
With a 1 MW cogeneration unit, the existing LNG gas station was sufficient, but after increasing capacity to 4.4 MW, the cogeneration would consume almost twice as much gas as the station could supply without freezing. To solve this, we expanded the LNG regasification station, more than doubling its capacity, enabling supply to the engine and other processes in the facility.
Diversification of energy sources
Thanks to the expansion, the facility can now use not only cogeneration but also the CHP and gas boiler. This allows flexible energy production management. Depending on the demand for different media – steam, electricity, or heat – installations can be used interchangeably or combined.
System integration
Designing and integrating all new and existing installations, such as the gas boiler, coal CHP, and cogeneration unit engine, was key to achieving the facility's full energy efficiency. Designing all installations and connections and obtaining permits took about a year. At Schumacher Packaging, almost the entire thermal energy installation was designed and executed by the DB Energy engineering team.
We complemented the system with control and monitoring systems, allowing ongoing parameter oversight and optimization of installation operation.
Results
- 21.8 million PLN – total investment cost in the cogeneration unit.
- ~40% of the plant's energy demand covered by cogeneration alone.
- 9 MW of electricity produced for the plant's own needs (total, including other installations).
- 3 years – estimated payback period.
- Increased energy security and diversification of power sources.
Conclusions
The project at Schumacher Packaging demonstrates how a comprehensive approach to energy modernization – from audit, through design, to integration of multiple energy sources – achieves tangible technical and financial effects. Implementing LNG cogeneration on such a scale in southern Poland is an example of a bold investment that significantly increased the facility's energy independence.
The implementation shows that even with complex challenges – such as the need to expand the LNG regasification station, integrate with existing infrastructure, or change the project scale – proper planning and engineering experience enable effective execution.
Within about three years, the installation will fully pay off, and the facility will benefit from lower energy costs and greater supply stability, providing a strategic competitive advantage for Schumacher Packaging.
Download case study
Schumacher Packaging (now Saica Group) is one of the largest producers of paper packaging in Europe. The company specializes in producing corrugated and solid board packaging, delivering its products to various industrial sectors worldwide.
Nasze najnowsze realizacje, które Cię zainteresują
The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków
The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.
Przejdź do artykułuHigher production and lower emissions – a chemical industry client on the path to net zero
At a chemical plant in southern China, we developed a 4-month strategy to reduce emissions by 70%, enabling increased production while lowering energy consumption and laying the groundwork for achieving net zero by 2035.
Przejdź do artykułuZero-emission in practice – emission reduction in pharmaceutical chemistry
Zero-emission in the chemical industry is not theory but concrete action. For a client in the pharmaceutical sector, we prepared a CO₂ reduction roadmap and implemented an incinerator modernization with heat recovery. The result? 12 GWh of thermal energy saved, a reduction of 2,172 tCO₂, and a quick payback period.
Przejdź do artykułu
Czekaj