Zero-emission in practice – emission reduction and energy optimization in pharmaceuticals

Zero-emission in practice – emission reduction and energy optimization in pharmaceuticals

Zero-emission in the chemical industry is not a theory but concrete action. For a client from the pharmaceutical sector, we prepared a CO2 reduction map and implemented an incinerator modernization with heat recovery. The result? 12 GWh of saved thermal energy, a reduction of 2,172 tCO2, and a quick payback period.

The challenge

The client – a global pharmaceutical producer – was looking for real ways to reduce the energy intensity of its plants in Europe and to define a pathway to full zero-emission.

Key challenges we faced:

  • lack of a comprehensive action map leading to climate neutrality,
  • high consumption of thermal energy and natural gas,
  • infrastructure modernizations carried out fragmentarily, without optimal sequencing and synergy effects,
  • the need to reconcile corporate requirements (100% emission reduction) with profitability of actions.

Our approach

DB Energy engineers
DB Energy engineers

We started with an energy audit and strategic workshops with the client’s engineers. Based on this:

  • we built a CO2 reduction map for the Irish plant as a pilot,
  • we indicated priority modernizations by costs, energy savings, and environmental impact,
  • we challenged earlier estimates (the client assumed 7% possible savings – DB Energy showed 25%),
  • we developed the concept of incinerator modernization with heat recovery as the foundation of the first stage of zero-emission.

The first step of our cooperation was formulating the key problems and assumptions related to a plant located in Ireland. The company’s goal was, among others, to develop a CO2 reduction map leading to the plant’s zero-emission and to reduce production energy intensity. Thanks to the collaboration of local engineers and DB Energy engineers, we defined a modernization path for the plant’s infrastructure. Later, it served as a map on the road to zero-emission. We also received information that the energy efficiency team operating within the client’s organization assessed the potential energy savings of the Irish plant at about 7%. This turned out to be a significant underestimation. Just one of the proposed modernizations saved about 12 GWh of thermal energy annually – about ¼ of the plant’s entire consumption.

Solution

  • Incinerator modernization – adapting it to burn both saline and non-saline waste,
  • Construction of a waste heat boiler – recovery of heat from the combustion process and its reuse in production,
  • Infrastructure optimization – limiting the need for a second incinerator to emergency function,
  • Further steps – electrification of processes and transition to RES in subsequent stages.
DB Energy team implementing the project at the plant
DB Energy team implementing the project at the plant

Project implementation

One of the issues at the client’s plant was implementing modernizations in different parts of the facility that were not always aligned with efficiency. From our experience, in many cases plants attempt to modernize infrastructure but avoid optimization in production processes. Sometimes, due to the lack of a proper strategy, actions may reduce consumption in one place while offsetting it in another.

Road to climate neutrality

At the client’s facility in Ireland, we planned a detailed roadmap that indicated the optimal sequence of implementing actions in terms of achieved energy savings, CO2 emission reductions, and required costs:

Road to climate neutrality implemented at our pharmaceutical client’s facility, developed based on conducted audits
Road to climate neutrality implemented at our pharmaceutical client’s facility, developed based on conducted audits

After implementing the investment plan aimed at reducing emissions and energy demand, we identified further steps to electrify the plant and green its energy sources. The key investment, from both energy and technological perspectives, was the modernization of the incinerator to allow the combustion of both saline and non-saline waste, along with the construction of a waste heat boiler in this system.

The idea of modernizing the incinerator resulted from audit findings and on-site work at the client’s plant, allowing heat recovery from combustion processes. This modernization falls within the first stage of the zero-emission strategy and is one of many steps the plant must take to achieve 100% net greenhouse gas emission reduction. Thanks to a flexible approach to investment, we can achieve better results and tailor solutions to the client’s needs.

Thanks to just one modernization, annual CO2 emissions decreased by as much as 2,172 tons. This is equivalent to driving around the world by car 400 times.

Effects

Chemical industry - DB Energy
DB Energy for the chemical industry
  • Investment cost: PLN 16 million
  • Annual thermal energy savings: ~12 GWh (approx. 25% of total plant consumption),
  • Emission reduction: 2,172 tCO2 annually (equivalent to 400 trips around the world by car),
  • Natural gas savings thanks to operating only one incinerator,
  • Payback period: ~5.5 years (shortened to 2.5 years thanks to an AENA subsidy of ~PLN 6 million).

Conclusions

  • A zero-emission strategy requires a systemic approach – individual modernizations, without a coherent action map, bring only short-term effects.
  • Actual savings can be greater than the client’s estimates – our analyses showed potential 3–4 times higher than internal assessments.
  • Heat recovery and modernization of key processes (e.g., incinerator) are high-return investments bringing both environmental and economic benefits.
  • Zero-emission in the pharmaceutical industry is possible – but it requires integration of actions at the corporate scale and cooperation with a technical-strategic partner.

This investment was important not only due to the reduction of CO2 emissions but also due to natural gas savings. Before modernization, the client used the main incinerator for non-saline waste and the second (reserve) incinerator for saline waste. Thanks to our investment, the main incinerator can now burn both waste types. The second incinerator will serve as an emergency unit, used only during overhauls or maintenance of the main one, which consequently leads to savings in natural gas consumption and related costs.

The corporation commissioning the investment is a major player in the pharmaceutical market. It has branches worldwide and employs over 1,100 people in Ireland alone. The main area of activity of the facility is the production of active pharmaceutical ingredients (API: Active Pharmaceutical Ingredients).

Nasze najnowsze realizacje, które Cię zainteresują

The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków

The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.

Przejdź do artykułu

Higher production and lower emissions – a chemical industry client on the path to net zero

At a chemical plant in southern China, we developed a 4-month strategy to reduce emissions by 70%, enabling increased production while lowering energy consumption and laying the groundwork for achieving net zero by 2035.

Przejdź do artykułu

Zero-emission in practice – emission reduction in pharmaceutical chemistry

Zero-emission in the chemical industry is not theory but concrete action. For a client in the pharmaceutical sector, we prepared a CO₂ reduction roadmap and implemented an incinerator modernization with heat recovery. The result? 12 GWh of thermal energy saved, a reduction of 2,172 tCO₂, and a quick payback period.

Przejdź do artykułu
Czekaj

Czekaj