Steam turbine installation for electricity generation – energy loss recovery in industrial processes
Instead of wasting energy on steam parameter reduction in a cooling station, the chemical plant used it to produce its own electricity. The installation of a steam turbine with a synchronous generator made it possible to utilize over 87 GWh annually and significantly reduce electricity purchase costs from the grid.
The challenge
In many industrial plants, including the chemical industry, steam boilers are used for process purposes. Steam exiting the boiler has high pressure and temperature parameters, which are then reduced to the level required by technological installations – usually in pressure-reducing and cooling stations. This mode of operation means that a significant portion of the primary energy is irretrievably lost instead of being used in the process of energy production.
In the analyzed plant, the challenge was to find a solution that would allow the energy lost during steam parameter reduction to be utilized while simultaneously reducing electricity purchase costs from the grid.
Our approach
Already during the preliminary analysis, we noticed that the plant was losing a huge energy potential during process steam reduction in the cooling station. Therefore, we proposed an alternative in the form of a steam turbine with a synchronous generator, which enables energy recovery from steam expansion.
We conducted detailed measurements of boiler and pressure-reducing and cooling station parameters, and then prepared a complete project concept along with a profitability analysis. A key element was matching the turbine to the plant’s variable demand profile and ensuring that the generated electricity would be fully utilized for production process needs.
Solution
DB Energy proposed replacing the pressure-reducing and cooling station with a steam turbine system coupled with a synchronous generator. As a result, the steam expansion process – previously causing losses – was transformed into a source of electricity generation. The turbo set produces energy directly used for the plant's own needs, which additionally reduces transmission losses and improves the overall energy balance of the facility.
During the preparatory stage, DB Energy conducted measurements and energy balance calculations, confirming the potential for energy recovery. Next, a complete modernization project concept was developed, including turbine and generator selection and integration with the existing steam infrastructure.
Results
The investment implementation brought significant energy and financial benefits:
- reduction of energy losses resulting from steam expansion,
- electricity generation for the plant's own needs,
- improved fuel efficiency in the steam boiler,
- reduced electricity purchase costs from the grid.
Overall, the investment allowed savings of over 87 GWh annually, with a payback period of approximately 4.5 years.
Conclusions
The installation of a steam turbine with a synchronous generator is an example of a solution that allows existing energy processes in a plant to be used for additional electricity production. Instead of irreversibly losing energy in the pressure-reducing and cooling station, the plant gains a real source of savings and improves energy security through partial independence from external electricity suppliers.
Nasze najnowsze realizacje, które Cię zainteresują
The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków
The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.
Przejdź do artykułuHigher production and lower emissions – a chemical industry client on the path to net zero
At a chemical plant in southern China, we developed a 4-month strategy to reduce emissions by 70%, enabling increased production while lowering energy consumption and laying the groundwork for achieving net zero by 2035.
Przejdź do artykułuZero-emission in practice – emission reduction in pharmaceutical chemistry
Zero-emission in the chemical industry is not theory but concrete action. For a client in the pharmaceutical sector, we prepared a CO₂ reduction roadmap and implemented an incinerator modernization with heat recovery. The result? 12 GWh of thermal energy saved, a reduction of 2,172 tCO₂, and a quick payback period.
Przejdź do artykułu
Czekaj