Modernization of the blower on the evaporators in the metallurgical plant

Modernization of the blower on the evaporators in the metallurgical plant

The modernization of the process blower enabled the reduction of pressure losses and energy consumption in the metallurgical plant. Thanks to the new blower station and improved air regulation, the client achieved annual energy savings of 7.82 GWh.

The challenge

Process installations in the metallurgical plant operated based on electrolyte evaporators powered by gas.

At the time of the audit, supplying the evaporators with air was done using old blowers without regulation capabilities, which resulted in high energy consumption. Air was transported to the evaporators over long distances through the process blower pipeline.

The nominal air demand for 7 operating evaporators was around 16,660 m3/h (an average of 2,380 m3/h per evaporator) at a minimum pressure of 0.07 MPa.

Our approach

The DB Energy team carried out:

  • detailed calculations of the cost of producing compressed air and blower operation,
  • measurements of air flow and pressure in the process blower pipeline,
  • assessment of the possibility to install a new blower station closer to the evaporator to reduce pressure losses and increase system efficiency.

Based on this, a modernization plan was developed, considering device capacity and regulation capabilities, minimizing the need for additional compressed air.

DB Energy engineer at work
DB Energy engineer at work

Solution

Evaporators - modernization of the process blower
Evaporators - modernization of the process blower

The modernization included:

  • installation of a new blower station directly at the operating evaporators,
  • selection of device capacity to eliminate the need for additional compressed air,
  • implementation of modern blowers with higher efficiency and improved regulation properties,
  • shortening of air pipelines, reducing pressure and energy losses.

The total investment cost amounted to 1.1 million PLN.

Results

The modernization of the evaporator blower resulted in:

  • reduction of energy consumption: 7.82 GWh per year,
  • financial savings: 1.9 million PLN per year,
  • reduction of pressure losses in the pipelines and improved efficiency of air transported to the evaporators,
  • improved regulation and system stability,
  • shorter response time to changes in air demand by the evaporators.
Savings - industrial energy efficiency

Conclusions

The modernization of the process blower shows that locating the blower station closer to process equipment and using modern regulation devices can significantly reduce energy costs and increase system efficiency.

Investment in the modernization of the compressed air system is quickly recoverable and brings measurable savings for the industrial plant.

Nasze najnowsze realizacje, które Cię zainteresują

The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków

The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.

Przejdź do artykułu

Higher production and lower emissions – a chemical industry client on the path to net zero

At a chemical plant in southern China, we developed a 4-month strategy to reduce emissions by 70%, enabling increased production while lowering energy consumption and laying the groundwork for achieving net zero by 2035.

Przejdź do artykułu

Zero-emission in practice – emission reduction in pharmaceutical chemistry

Zero-emission in the chemical industry is not theory but concrete action. For a client in the pharmaceutical sector, we prepared a CO₂ reduction roadmap and implemented an incinerator modernization with heat recovery. The result? 12 GWh of thermal energy saved, a reduction of 2,172 tCO₂, and a quick payback period.

Przejdź do artykułu
Czekaj

Czekaj