Removal of leaks in the compressed air system
Compressed air leaks are one of the most common sources of energy losses in industry. Thanks to the audit and repair works by DB Energy, a client from the construction sector reduced energy consumption by 2.21 GWh annually, achieving a quick payback period.
The challenge
Compressed air is one of the most expensive energy media in industrial facilities – its production consumes significant amounts of electricity. In many enterprises, serious losses occur due to system leaks. Statistically, in 80% of plants in Europe, leaks account for 25–30% of total air consumption. Our experience shows that this is a common problem also in Poland.
In one construction sector client, an energy audit revealed a significant level of leaks, resulting in high energy costs and additional load on compressors.
Our approach
The DB Energy team conducted:
- a detailed inventory of the compressed air installation,
- flow and pressure measurements at various points of the system,
- leak detection using specialized ultrasonic devices,
- cost analysis of potential energy losses and effects of planned repairs.
A key element was not only eliminating identified leaks but also indicating areas with a higher risk of recurrence. As a result, the plant received a preventive plan including regular monitoring and maintenance of the system.
Solution
As part of the project, repair works were carried out at critical points of the compressed air system:
- sealed connections and fittings,
- replaced worn system components,
- optimized compressor settings after air loss reduction.
Investment outlays amounted to approx. PLN 170,000, which is relatively low compared to the scale of achieved savings.
Results
The project implementation brought tangible benefits:
- energy savings: 2.21 GWh annually,
- energy cost reduction: PLN 574,600 per year,
- simple payback period: under 6 months,
- increased reliability and stability of compressor operation,
- reduction of CO2 emissions.
Conclusions
Repairing compressed air leaks is one of the most cost-effective efficiency actions in industry. The example of a construction sector client shows that even a relatively small investment can result in million-scale savings over a few years. Regular monitoring and systematic leak removal should be a permanent element of the energy management strategy in industrial plants.
Nasze najnowsze realizacje, które Cię zainteresują
The largest LNG-powered cogeneration unit in southern Poland – Schumacher Packaging Myszków
The largest LNG-powered cogeneration unit in southern Poland is now operating at Schumacher Packaging in Myszków. Thanks to an investment of 21.8 million PLN, the facility has achieved nearly 80% energy independence, producing almost 9 MW of electricity and significant amounts of heat. The project, implemented by DB Energy, demonstrates how an energy audit can serve as a starting point for a comprehensive energy transformation of a factory – from modernization of existing heat sources, through energy recovery, to the implementation of advanced cogeneration.
Przejdź do artykułuHigher production and lower emissions – a chemical industry client on the path to net zero
At a chemical plant in southern China, we developed a 4-month strategy to reduce emissions by 70%, enabling increased production while lowering energy consumption and laying the groundwork for achieving net zero by 2035.
Przejdź do artykułuZero-emission in practice – emission reduction in pharmaceutical chemistry
Zero-emission in the chemical industry is not theory but concrete action. For a client in the pharmaceutical sector, we prepared a CO₂ reduction roadmap and implemented an incinerator modernization with heat recovery. The result? 12 GWh of thermal energy saved, a reduction of 2,172 tCO₂, and a quick payback period.
Przejdź do artykułu
Czekaj